[v2] Define the v1-to-v2 integration and release plan #2526

Description

@SteveSandersonMS

Summary

Produce the approved procedure for maintaining, testing, and merging v2 changes without disrupting remaining v1 releases or existing main-based automation.

Current working position

  • Breaking v2 pull requests remain open against main while this procedure is unresolved.
  • Pull request owners may rebase independently as main moves.
  • No breaking v2 pull request merges until this issue records an approved plan.

Plan requirements

  • Define how the open v2 pull requests are tested as a combined change set.
  • Define the merge order and handling of conflicts between overlapping pull requests.
  • Choose whether integration happens directly over a short merge window or through a temporary integration branch.
  • Identify the final planned v1 release and whether any v1 servicing is required afterward.
  • Preserve existing main-based release automation unless an explicit automation change is approved.
  • Define v2 preview versioning, publishing, and validation.
  • Define the criteria and responsible maintainers for promoting v2 to stable.
  • Include freeze points, rollback handling, and the explicit gate allowing the first breaking change into main.

Completion

Maintainers approve and document a step-by-step procedure that can be followed when the implementation pull requests are ready. This issue is complete when the plan is actionable, not merely when alternatives have been discussed.

Activity

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Type

    No type

    Projects

    No projects

      Milestone

      No milestone

      Relationships

      None yet

      Development

      No branches or pull requests

      Issue actions